Your First Visual Tracking Application - Part One

Filed under: FANUC Line Tracking Vision

Visual tracking is intimidating, much more intimidating than most other material handling applications. With all the additional hardware required (cameras, encoders, multiplexers) and steps to get things moving (camera calibration, tracking frame calibration, vision process creation, reference setting, accuracy tuning), it’s easy to get overwhelmed. And you haven’t even made any of your other extremely important decisions yet: what robot(s) should I use? What is the best layout for this application? Should I use parallel flow or counterflow? What type of gripper should I use? Can I get away with a single-pick gripper, or should I design one that picks two at a time? Should I use PickTool, or should I write it all from scratch? Lots of questions, difficult answers.

Just like eating an elephant, let’s tackle this problem one bite at a time:

  1. Gripper
  2. Vision
  3. Robot Selection
  4. Layout
  5. Number of Robots
  6. Relative Conveyor Flow Direction
  7. Hardware
  8. Setup
  9. Programming

That list doesn’t look so bad anymore. I’m going to cover the entire list in two parts. In part one (this post), I’ll go through items 1-5, and I’ll address items 6-9 in next week’s post.

1. Gripper

Your gripper design is absolutely crucial to the success of your visual tracking application. As with any other application, your $60k robot isn’t worth much if it can’t reliably handle your parts at the required speeds. Because visual tracking applications often end up being multi-robot, your gripper design can easily save (or cost) you a robot or two.

Do extensive testing with your actual product. Make sure to do it at full speed over the entire range of motion. What happens if you push the robot even harder? Can the gripper hold on to the product while rotating it? How long can the gripper hold on before damaging the part? How long does the gripper take to actuate? Is there any way to reduce that time? Is there anything the gripper can do that will make the robot’s job easier?

Testing takes time and money, but it will save you both in the long run. I’ve seen too many projects drag on with revision after revision to the end-of-arm tool with arguable levels of success.

I personally prefer single-pick grippers, or at least a gripper that picks its entire payload in one pick-cycle. Making that second pick while holding onto another part is a lot more difficult. (Will the first part be in the way? With all the potential for rotation, does the second gripper slot really save you any time?)

2. Vision

Often an afterthought, reliably recognizing your products is extremely important. Not only do you have to make sure you can accurately identify the position and probably orientation of your parts, but, when tracking, you have to do it quickly.

Lighting is key, so is the color of your conveyor. Use a lens filter! Make sure to pick a lens and standoff distance so you have a wide enough field of view (FOV) that minimizes perspective distortion.

Your conveyor speed and FOV determine how often you need to trigger the camera.


                              1
  FOV length (mm) * --------------------- = minimum trigger interval (s)
                    conveyor speed (mm/s)
 

If your vision process takes longer than your trigger interval, you’re going to get Vision Overrun errors. Those parts may never get into your tracking queue.

Of course you also need to snap often enough to not miss any parts. If you only snap once every FOV length, a part that’s only half-visible in the first shot will also be half-visible on the other side during the next snap. A good rule of thumb is to make sure your trigger distance is less than your total FOV length minus half the length of your largest part.


                    longest part length (mm)
  FOV length (mm) - ------------------------ = trigger distance (mm)
                               2
 

Vision is worth a post on its own someday.

3. Robot Selection

When FANUC first started pushing into the high-speed visual tracking market, picking a robot was easy. You could use the M-430iA/2F, and that’s about it. You might have been able to get away with an LR Mate, but if you’re conveyors were moving at any sort of speed, you probably needed the M-430iA. With the advent of their Genkotsu robots (delta), you have many more (and better) choices.

Right now, there are at least 8 different LR Mate 200iC models, the LR Mate 200iD aka the mini-Mate, 3 different M-1iA’s, 4 different types of M-2iA and 2 different M-3iA variants. You may still be able to get an M-430iA, but you’d probably be better off with one of these other options.

Which robot should you choose? Personally I would look at a delta robot first. They are built specifically for these types of applications, and they don’t suffer from some of the nasty limitations that articulated robots have when trying to do these jobs. Chances are a single delta robot can do the job of two LR Mates, and it may end up being cheaper. Just be careful here since your gripper will have to do twice as much work twice as fast.

Don’t use more axes than you need. If it can be done with a 3-axis delta, don’t buy a 4-axis. If it can be done with 5 axes, don’t buy a 6-axis robot. Unless you’re looking to repurpose these robots later, you’ll save money and probably have better performance.

Keep in mind that an articulated robot can essentially only use half of its work envelope. If you mount it on a pedestal, it can probably only use the area directly in front of it. Even if you hang the robot upside-down, the area directly underneath the robot is a dead-zone which becomes very troublesom while tracking. Be careful when using an articulated arm.

4. Layout

Once you are pretty confident in your gripper design and have a favorite robot, it’s time to start thinking about layout. Layout is always important, but it’s especially important when you’re trying to do something extremely fast at the upper limit of the robot’s capability.

It’s tempting to throw a work envelope on top of your proposed layout and call it done if the robot can reach, but have you considered the distance the robot will need to track? Boundaries are hard to get right, and they’re really hard to work with if you get limit errors all over the place. You shrink your boundaries to fix the limit errors only to start getting track destination gone errors. Battling a bad layout after everything is built is the worst.

Now try out your layout and robot in ROBOGUIDE. Don’t have ROBOGUIDE? Stop now. Do not pass Go. You heard me right: don’t even bother attempting a high-speed visual tracking application without simulating it, especially if it looks like it’s going to be more than one robot. The dynamics of these systems make them very difficult to estimate. You really have to spend a lot of time in simulation putting different stresses on the system to get a feel for how it will perform. Use very conservative gripper delays and run your conveyors faster than you expect. See where the system’s breaking point is and give yourself some room.

You may be able to get some help or advice from FANUC’s Material Handling Segment or a regional office, but remember that it’s your project. Don’t blindly accept their advice. Ask stupid questions. Try to break their assumptions. Stress the system. Your customer’s not going to be happy when your excuse for a lagging system is “FANUC said it would work.”

As with any application, try to make things easy on the robot. Optimize both horizontal and vertical motion. Does the robot really need to go all the way into that box? Can you use extending and retracting cylinders to save on some vertical motion? Are they fast enough?

If the system is going to have more than one robot, consider the spacing between them. Will they interfere with eachother? Notice how moving a robot upstream or downstream within multiples of your part-length affects how the robots share work.

5. Number of Robots

This is a big decision, and it depends completely on steps 1, 2 and 3. If you’re simulating that you are on the very edge of using 1 vs 2 or using 2 vs 3, you may want to go back and see if you can do something to give yourself a bit more room. Keep in mind that a single robot doesn’t have to worry about load balancing, and load balancing is very different between 2 robots vs. 3, 4, 5, etc. You can’t just say 1 robot can do 100 parts per minute, so 10 can do 1000ppm.

If one delta robot looks like it can barely handle the application, you may be better off using two articulated arms. The cost will probably be similar, you’ll probably have a little room to spare, and your gripper performance becomes less crucial.

Next week…

Next week I’ll talk about my thoughts on parallel flow vs. counterflow, hardware requirements, setup and programming. In the meantime, send me an email or leave a comment if you have any questions.


There's more where that came from.